For now, Cedar Park's biggest new development is one building. Scheels opened at 2150 Cedarview Drive on Aug. 29, 2026. The furniture anchor, the hotel and both announced restaurants are still on their way. For the rest of this year and probably into spring, a CedarView trip means a Scheels trip, with a road widening going on around you.
Scheels was built to fill an afternoon. Beyond that, the useful questions are when everything else arrives and how much each date can be trusted, since they range from a state construction filing to a spokesperson's rough estimate.
What one building holds right now
The store is more than 300,000 square feet. It is the company's 35th location in 16 states and its second in Texas. Community Impact reported that it ranks among the largest retail spaces in the state. On a weekend, though, the square footage matters less than the non-shopping attractions. According to the company's opening announcement and local coverage, they include:
- A 65-foot indoor Ferris wheel. Tokens cost $1 on Scheels' Cedar Park checkout page. Riders must be at least 36 inches tall, and children under 48 inches ride with a responsible adult.
- A 16,000-gallon saltwater aquarium holding roughly 600 fish.
- A custom wildlife mountain and sports simulators.
- Fuzziwig's Candy Factory, which the Austin American-Statesman listed among the store's draws at opening.
- Ginna's Café, which Community Impact described as serving soups and sandwiches.
Put together, a family can ride the wheel, look at the aquarium and eat lunch for a few dollars without buying any gear. None of CedarView's announced restaurants has an opening date yet, so if you're planning a long visit, the café is where lunch happens.
The store also brought jobs. Scheels said it hired more than 500 associates for Cedar Park ahead of opening, including 100 full-time and 350 part-time new local hires.
Two dates on the Scheels calendar before the year ends
The store's Cedar Park events page currently lists two events.
Fashion After Hours, Sunday, Nov. 1, 7:30 to 9:30 p.m. Tickets cost $25, and you get the full amount back as a Scheels gift card when you check in. In practice it's a free evening in the store if you planned to shop anyway.
Holiday LEGO Build, Dec. 12 and 13. The event is free but requires registration. It's recommended for ages 6 and up, and a parent or guardian has to stay for the whole build.
Everything else, sorted by how solid the date is
Every other CedarView name you've heard is still under construction or still being planned. The dates attached to them come from very different kinds of sources, and that tells you how much each one can move.
| Coming to CedarView | Location | Stated timing | What the date rests on |
|---|---|---|---|
| J. Alexander's | 750 E. New Hope Drive | Estimated completion Nov. 30, 2026 | State construction filing; no opening date announced |
| Marriott hotel and conference center | CedarView | April 2027 | Hotel sales and marketing director, September 2026 |
| NFM | CedarView | 2027 | NFM's own Austin store page |
| Haywire | 1005 E. New Hope Drive | Late 2027 | Company spokesperson, June 2026 |
J. Alexander's has the nearest date and the most paperwork behind it. Its Texas Department of Licensing and Regulation filing, TABS2026004969, describes a 9,504-square-foot, $4.25 million project with a planned start of March 31, 2026 and an estimated completion of Nov. 30, 2026. That is an estimated finish for the building. It is not an opening date. Community Impact reported in November 2025 that the restaurant expected to open in fall 2026, while also noting that no official date had been set. CedarView's own December 2025 announcement said J. Alexander's intended to open alongside NFM and Scheels. Scheels has opened and NFM hasn't, so that plan no longer fits a single date. A late-2026 opening is possible. Early 2027 is just as reasonable a guess.
The Marriott is designed to carry 297 rooms, 30,000 square feet of meeting space and five food and drink venues: a Mediterranean restaurant, a French-inspired café, a pool bar, a lobby bar and a Marriott Bonvoy M Club. Those five venues would add places to eat and drink that are open to people who will never book a room there.
NFM is the development's anchor. Its Austin store page now gives the opening as simply "2027." An earlier company announcement had said Spring 2027, and the current page no longer names a season. Even so, the preparations are concrete. Community Impact reported Oct. 8 that NFM plans to hire about 700 Austin-area employees and expects roughly 400 current employees to relocate to Cedar Park. Hiring for sales, warehouse and delivery roles started this fall. The store will be NFM's second in Texas, after The Colony in North Texas.
Haywire is the furthest out. Community Impact reported in June 2026 that construction would begin in eight to nine months and that the restaurant expected to open in late 2027. The plan is a build of more than 10,000 square feet with a large outdoor area. That timeline puts the start of construction in early 2027, so the opening date is still mostly a plan.
Spring 2027 is when the road and the district line up
The road work is the other half of the picture. New Hope Drive is being widened from four lanes to six between Block House Drive and CR 180. The project costs $49.5 million, and the city's projects dashboard targets completion in spring 2027. In late July, the city said signals at New Hope and Enchanted Rock Drive would be fully live July 30, and that work at the New Hope and Main Street–Block House intersection was expected to be done by the time Scheels opened. Lane shifts on the rest of the corridor will continue until the widening is done.
The 183A Toll interchange has been rebuilt, too. The left turns from the northbound and southbound frontage roads onto New Hope now follow a changed route, though the city says every direction of travel is still available. If you haven't been through it since spring, plan on the turn feeling unfamiliar.
Lay the schedules side by side and they converge. The widening targets spring 2027, the Marriott targets April 2027, NFM says 2027, and J. Alexander's building should be finished well before any of them. Haywire follows in late 2027. That means the road is scheduled to reach six lanes at about the time CedarView goes from one destination to several. From now until then, you're visiting one store on a road that is still under construction.
Making the trip in the meantime
- Go early or on a weekday. A KXAN Studio 512 segment on the store suggests arriving early in the day or on a weekday, when it's likely to be less crowded than at peak weekend hours.
- Bring a few singles' worth for the wheel. Tokens are $1 each.
- Measure young kids before you promise a ride. Riders have to be at least 36 inches tall, and anyone under 48 inches rides with an adult.
- Check your route into New Hope. The 183A frontage-road left turns use the newer layout, and lane shifts toward CR 180 continue through the widening.
- Put Dec. 12 or 13 on the calendar now if your kids would enjoy the free LEGO Build, since it requires registration.
We pay attention to developments like CedarView because the openings closest to home change how a neighborhood works day to day well before they show up in a list price. If you're in Cedar Park and wondering what 2027's openings and the New Hope widening might mean for your street or your plans, Taute Homes is glad to talk it through over coffee, or after a ride on the Ferris wheel. Let's Connect.